Expanding the Center Timeline

 

March 2017

  • Sign new lease   √

April 2017

  • Research landscape partners   √
  • Begin garden schematics and concept   √

May 2017

  • Refine garden schematics and concept   √

June 2017

  • Finalize garden design √
  • Begin Phase I: Expanding the Center fundraising campaign √

August 2017 (anticipated)

  • Receive estimate for final garden design
  • Sign landscape contract

September 2017 (anticipated)

  • Complete roof replacement ** Short-term closing expected

October 2017 (anticipated)

  • Begin initial garden installation
  • Begin Suite C building remodel

November 2017 (anticipated)

  • Complete Suite C building remodel
  • Begin Suite D building remodel

December 2017 (anticipated)

  • Complete Suite D building remodel
  • Complete initial garden installation

Winter 2018 (anticipated)

  • Begin and complete Suite B building remodel

Spring 2018 (anticipated)

  • Begin and complete final garden installation